Overhauling Sugar Mill

Triveni 5 MW Back-Pressure Turbine — Full Overhaul & Rotor Balance

2023 12 days Confidential — Sugar Mill, Western UP

Scope of Work

Complete turnkey overhaul: rotor removal, bearing replacement, labyrinth seal machining, rotor dynamic balancing (ISO 1940 G2.5), lube oil flushing, and commissioning.

The Challenge

The turbine had been running with elevated vibration (>6 mm/s) for two seasons. Bearing housings showed fretting wear and the rotor had a persistent 1× runout that previous maintenance had not resolved.

Our Solution

Our engineers, with prior Triveni experience, disassembled the unit and found a cracked journal on the drive end. The journal was machined undersized, new Babbitt poured and scraped, labyrinths machined in our workshop, and the rotor dynamically balanced to <0.5 g·mm residual imbalance. Post-commissioning vibration: 1.8 mm/s.

Measured Outcomes

  • Vibration reduced from 6.4 mm/s to 1.8 mm/s
  • Bearing metal temperature dropped by 14 °C
  • Turbine returned to service within the planned 12-day window
  • No unplanned trips in the subsequent 12-month operating season

Have a Similar Requirement?

We handle Overhauling jobs across all major OEM brands and industries.

Tell us your turbine make, capacity, and symptoms — we respond with a technical answer, not a brochure.

Find Us Online

Find us on

Our business profiles on Google, IndiaMART, TradeIndia, ExportersIndia and JustDial.

Call NowWhatsApp